Cruise the Ville
August 18, 2012 Whetstone Park Click here or the logo for official registration form. For more info go to
Click the logo for Farmer's Market Information & Registration
The Clintonville Area ©2000 Clintonville Area
|
High
Street Improvements
Public Update Meeting Scheduled for April 13th Paving the Way and the Chamber will host a public meeting on Wednesday, April 13, 2005, at 7:00 p.m. at North Broadway United Methodist Church. Representatives of the City Transportation Department and the construction contractor will be on hand to answer questions and provide information on the status of the project and the proposed construction schedule for the remainder of the summer.
From the On Site Project Manager Construction resumed on March 23,2005 and began in Phase 1, Sector 2, on the East side of High Street between Weber and Como. Work will continue on this side of the road up to Torrence and then cross over to the West side and proceed South toward Arcadia. Work is expected to be completed this Fall. Parking will be allowed in the work zones before Weber and after Como however, signage will not be posted. The City reserves the right to rescind parking in these areas if it becomes a safety hazard. Beginning Monday, April 11, The Clintonville field office will be open to the public if they wish to review the plans. These hours will be from 9:00 A.M. to 2:00 P.M. M-F. Other times can be made available by scheduling a time through me. As with last year, please do not remove plans from the office and close the door upon leaving. A project schedule will be posted in the window at the office building at 3400 N High Street for anyone who is interested in the construction progress. Should anyone have any questions or issues regarding the construction process, they are free to call me at the number below.
Thanks
Doug Daily Engineer Associate III Transportation Division 374-6520 (mobile) 246-7146 (office)
City and Construction Company Now Have Office in Clintonville The City of Columbus and Columbus Asphalt have open a project construction office at 3400 N. High St. on the second floor. The on-site manager is Doug Daily, 374-6520.
*Project meetings are now being held bi-weekly. The next meeting will be November 10, 2004 at 1:30 P.M.
- *The front office at 3400 N. High Street, Suite 220, will be open to anyone in the project area who has an interest in viewing the project plans. This is effective as of November 1, 2004. A set of Plan and Profile sheets (full scale drawings) and complete set of ½ scale drawings on the desk in this office. Project manager does not need to be in the office for anyone wishing to view them. Do not removed from the room and close the office door when you leave.
*Should anyone have questions or issues, they only need to call Doug Daily and he will be able to meet with them. Doug will have this office open at a minimum of between 9:00 and 3:00. If this is not convenient for some, I can make arrangements with them individually.
Page down for additional contacts relating to the High Street Improvements.
Mayor and City Council Strike Blow for Clintonville!
Mayor Michael Coleman, City Council President Matt Habash and Councilwoman Maryellen O'Shaughnessy came to Clintonville for the official "curb-breaking" to kick off the High Street Improvements project.
Clintonville resident Pete Cass also took a turn at the official "Curb-Breaking" ceremony.
Non Rush Hour Parking Permitted
High Street lane restrictions and parking restrictions have been eased a bit. Parking is now permitted on the west side of High St. in the construction zone in non-rush hour times. However, there is still no parking between 7:00 - 9:00 a.m.
|
|||||||||||||||||||||